Project Spotlight: Rapid Fireproofing Solution
February 6, 2026
Project Challenge / Design Obstacle:
- Customer needed a 1-in-3-hour fire-rated firewall.
- Minimal disruption to ongoing operations was critical.
Thermo-Guard Solution:
- Applied spray-applied cementitious fireproofing (Monokote MK-6 HY) directly to the existing metal structure.
- Completed the entire scope in just 2 days, allowing production to continue uninterrupted.
Results:
- Fire Marshal inspection passed the very next day—production resumed immediately.
- Avoided extended downtime, major reconstruction, and loss of usable space.
- Faster, more efficient, and roughly half the cost of traditional firewall construction.
Technical Note:
- Cementitious fireproofing creates a physical 3-hour fire-rated barrier, ideal for industrial metal buildings.
- Alternative: Intumescent coatings expand under heat, offering space-saving, thin fire protection—best for aesthetics or limited-clearance areas.
Quick Takeaway:
- Fireproofing can be fast, cost-effective, and minimally disruptive when the right system and product are selected.